The UIT Practice Area Director and/or UIT Project Manager typically drive the charter process, being sure to get input from all stakeholders during the elicitation and review process. Note: For all P2P and Core Financials projects, FMS will drive step 5, not the UIT Project Manager.
1
Step 1: Elicit
Gather project charter details and update the following sections in the Project Charter template:
- Section 1: Problem Statement, to be completed by business
- Section 2: Solution section, to be completed by UIT
- Remaining sections: to be completed in collaboration
2
Step 2: Analyze
Analyze all inputs and make sure the impacts listed below have been taken into consideration while preparing the charter. The points below are not intended to be a replacement for the Business Requirements Document, but rather a mental checklist for the charter so that you have included all the right stakeholders and, at a high level, have touched upon all the usual topics of our projects.
- Business process improvements
- Reporting and BI
- Authority and security
- Interfaces or impacts to other systems and departments
- Infrastructure and environment needs
- Outside vendor needs
- Integration with outside systems, such as systems outside of UIT or Stanford
- Campus readiness
- Expected support impacts
- Baseline data, if it exists and is not part of the charter itself
3
Step 3: Document
Draft the detailed charter, also known as Funding Project Charter. Make sure all financials foot, i.e., totals add up correctly and Excel formula ranges are accurate. Keep detailed back-up data such as spreadsheets.
4a
Step 4a: Tier 1 Review, Core Team Managers
Route charter to UIT and business for feedback. Allow a minimum of one week for this review; 24-hour notice is unacceptable! Primary driver/coordinator for review is the Project Manager.
List of UIT Functional areas to route to:
- Practice Area Director
- Practice Area Director(s) of other areas where impacts are cited
- Project Manager
- PMO, for tracking purposes
List of business functional areas to route to:
- Core stakeholders of sponsoring department
- Business owner(s)
- Supporting or impacted business owner(s) such as FMCS, OSR, etc.
Incorporate feedback before routing to next step.
4b
Step 4b: Tier 2 Review, Business Client and UIT Executives
Route charter to UIT and business stakeholder management for feedback. Primary driver/coordinator for review is the Project Manager.
Management to route to:
- Applicable UIT AVP(s)
- Business Client Executive(s) as applicable
Incorporate feedback before routing to next step.
5
Step 5: Present for CFO Approval
For SGG and Business Affairs Initiatives Projects Only: After everyone has provided their input and the charter version is final, schedule a meeting with Randy Livingston via his assistant, Ruby Stanfield. Be sure Noel Hirst and Shachi Chopra (or other assigned UIT Financial Analyst) are invited. Route charter to the CFO in advance of presentation.
Attendees of the presentation:
- Project manager
- UIT Director in whose practice area the project is being run
- Affected UIT AVP(s)
- Business Owner or Sponsor
- Business Client Executive
The Project Manager may start the presentation, but the Business Owner typically does the bulk of the talking. Be sure you have practiced the presentation ahead of time and primary speakers know what they need to say. Anticipate questions such as ROI (return-on-investment), metrics showing value and support for the project, solid business problem and solution, number of users impacted or affected by the project, streamlining of process that may be achieved by project, etc. Be sure to bring the resource plan to the presentation.
6
Step 6: File
Once the charter has been fully signed off, upload the final document to the "UIT PMO Project Financials" Google Team Drive. Do not post copies of the charter with financials anywhere else, due to the sometimes sensitive nature of that section. If you need to post a copy of the charter somewhere more accessible for your project team, post a copy with redacted financial data on your project's Google Team Drive.